BuildLabs Custom LLC ▾  ·  BL1091 - 57 Highway Behind the Pond ▾
WS
Project Home
Temporary model · read-only · built 2026-10-01 from live Procore and recorded QuickBooks figures · restyled 2026-10-12

57 Highway Behind the Pond

BL1091
ExportCreate ▾
East Hampton, NY 11937 · BuildLabs New York · Residential · AIA A105-2017 owner contract
Course of Construction Record: Procore (NY) Books: QuickBooks Desktop

Money

Procore prime contract + budget (live 10-01) · QuickBooks cost on file 09-22

Contract sum
$889,111
Amendment No. 1 restated; approved COs $0
Committed
$197,086
of $244,542 written across 12 commitments
Cost to date
$109,301
QuickBooks. Procore's figure: recheck (T-0410)
Billed to owner
—
Not on file: prime SOV empty, no owner invoices in Procore
Cost to date $109,301 Committed less cost to date $87,785 Uncommitted $720,207 Revised budget $917,293 (two budget changes, +$28,182)

Draft change orders waiting on the owner: 23, net +$106,320.40. If all were signed the contract would read $995,431.40.

The super's day: Punit's trigger point

Procore daily log counts per date (live 10-01) · the day closes only when every column is green

DayOn siteLog / notePhotosIn · out timesClose-out checkDay
Wed 09-30✓✓✗??Open
Tue 09-29✓✓✗??Open
Mon 09-28✗✓✗??Open
Sat 09-26✗✓✗??Open
Fri 09-25✓✗✗??Open
Thu 09-24✗✓✗??Open
Wed 09-23✗✓✗??Open
Tue 09-22✓✗✗??Open
Mon 09-21✓✗✗??Open
Sat 09-19✗✗✗??Open
Fri 09-18✓✗✗??Open
Thu 09-17✓✗✓??Open

✓ captured · ✗ missing · ? nowhere to capture it yet. Photos usually go to Procore's Photos tool, not the log, so a ✗ here may be filed elsewhere. In/out times and the close-out checklist have no field in any system, so no day can close yet. That is the gap the gate has to fill.

Changes

Procore change events (36) and prime change orders (23), live 10-01

Events open
35
1 void
Scope TBD
24
not yet ruled in or out of contract
Prime COs
23
all draft, none signed
Newest
CE 36
Lights + screens at pergola, 09-28

Commitments

Procore subcontracts and POs, live 10-01

No.ScopeAmountState
SC-003Site, excavation, drainage, sanitary (plans 3-20-26)$34,950.00Executed
SC-005Base plate and foundation$32,000.00Executed
PO-001Aluminum trellis (CE 4)$25,082.66Executed
SC-006HVAC$24,500.00Executed
SC-002Topsoil strip, garage + accessory excavation, sanitary$23,850.00Executed
SC-001Plumbing$22,500.00Executed
PO-003Colour-match parapet caps (CE 5)$18,908.60Executed
SC-004Steel$10,500.00Executed
PO-002reSAWN wood roof at spa (CE 26)$47,276.34Not executed
PO-004Simpson Strong-Wall$4,794.66Not executed
PO-005Simpson hold-down quote$179.66Draft
SC-007Crane for assembly$0.00Draft

Needs a decision

Open tickets and live reads

  • DateContract says 09-30-2026 (tentative); schedule V4 says 02-16-2027 at 40 %No executed instrument moves the date. T-0400, counsel's question.
  • BillingPrime schedule of values is emptyOwner billing against the seven milestones cannot run from Procore.
  • COCredit Stucco −$42,000 unsigned since 05-08If signed, the masonry package is $5,000 of walkways. T-0399.
  • POPO-002 reSAWN roof $47,276.34: approved, not executedCounts as written, not committed.
  • CostProcore cost side read as $0 on 09-22Probably the wrong view; QuickBooks actuals sit in the ERP Budget View. T-0410.
  • AccessTwo departed staff still active Procore users on this jobT-0394.

Details

Procore project record + owner contract

Started
2026-03-16
Finish
2027-02-16 projected · contract 2026-09-30 tentative
Payment
Seven milestones, % of contract sum (25 · 10 · 20 · 25 · 5 · 10 · 5)
Retainage
0 % on prime and every commitment
Contract type
Stipulated sum (A105). Under CH-02 §4.3 a super's hour is overhead here, not billed [proposed]
Box
Job folder: link goes here (folder id to bind)

People

Roles, not names: whoever holds the role sees this page

Client
Owner on the A105 (name differs between contract and QuickBooks; open)
PM
Project manager, NY
Site
Site super: closes the day
Contracts
Commitments + insurance desk
Hours
Hours verification (HOURS VERIFIED stamp)
Approves
Punit: what reaches the owner's bill

Project mail address

Procore already gives this project one (live 10-01)

CC this and the mail files to the project in Procore, the same idea as Clio's Maildrop. Nobody uses it today. A BuildLabs address (e.g. bl1091@) would file to the Box job folder instead.

com-inbound-57-highway-behind-the-pond-@us02.procoretech.com

Timeline

Procore events + daily logs, newest first

  • 09-30Day log: manpower, 2 work entries
  • 09-29Day log: manpower, inspection, work
  • 09-28CE 36 opened: lights and screens at pergola (3 lines)
  • 09-23SC-007 crane for assembly started as draft, $0
  • 09-21PO-002 and PO-004 updated
  • 09-18Schedule V4: client acceptance 02-16-2027, 40 % complete
  • 09-17Day log with 10 photos (the only photos in the log in two weeks)
  • 09-15CE 33–35: ducted HVAC, extra conduits, slab insulation
  • 09-10CE 32: new stake-out diagram / addendum
  • 09-09CE 29–31: material storage, gas service repair, extra siding